Czech Republic
07/2025
–
08/2025
49.5
kWp

In summer 2025, we completed a 49.5 kWp photovoltaic power plant installation on the headquarters building of STAVEBNÍ FIRMA PLUS s.r.o. in Hodonín.
The installation comprises 110 Longi monocrystalline panels (450 Wp/panel, 20.7% efficiency) mounted at a 25° tilt angle.
The estimated annual energy yield is 45,492.64 kWh, with a portion of the energy consumed on-site and surplus power (up to 30%) fed into the EG.D distribution grid.
Energy conversion is handled by two Solax X3 inverters rated at 25 kW each, equipped with surge protection and compliant with all technical and safety standards. The system is connected to the building's main distribution board and features automatic power regulation functions as required by the grid operator.