Česko
04/2023
–
06/2023
613.64
kWp
Construction of the photovoltaic power plant without battery storage took place from April to June 2023. On a total area of 6,000 m², 1,334 pieces of JA Solar 460 Wp photovoltaic panels were installed, which ensure efficient electricity production. This project uses cutting-edge Sungrow SG125CX inverter technology for efficient solar energy conversion.
Construction was supported by a grant of CZK 4,537,100.
The project was designed to maximize solar potential utilization of the given location and ensure long-term sustainability of the industrial facility's energy needs.