09/2022
–
06/2023
699.96
kWp
In 2022, the company headquarters moved to Hodonín, where a modern hall and offices were built in the Kapřiska industrial area. On the facility roof, we installed 1,842 pieces of JA Solar photovoltaic panels with 380 Wp capacity, which ensure efficient electricity production. This project uses cutting-edge Fronius Tauro and Fronius Symo inverter technology for efficient solar energy conversion.
Construction of the solar power plant took place from September 2022 to June 2023 and was supported by a grant of CZK 5,142,200.
The project was designed to maximize solar potential utilization of the given location and ensure long-term sustainability of the industrial facility's energy needs.